Penwortham Substation

Contract Works:

- Caisson shaft & cover slab (9m ø, 13m deep).

-The shaft was sunk within a live national grid 400kVa substation.

-All of our operatives were therefore BECS trained in order to ensure their safety and the safety of others whilst working within the substation.

-All of our operatives were therefore BECS trained in order to ensure their safety and the safety of others whilst working within the substation.

-The shaft was constructed via a jacked caisson and the base cast underwater.

-A 12 piece PCC cover slab was then installed on top of the shaft.